China C&I Energy Storage Project

Project Overview:

Wenergy partnered with Hunan Haili Lithium Battery Technology to implement an energy storage project in Changsha High-Tech Development Zone.

Operating on a peak shaving and load shifting model, the system ensures reliable power for Haili’s production. Completed in just 20 days, the project highlights Wenergy’s commitment to efficient and sustainable energy solutions.

 

Location:Hunan,China

Scale:1.44MW / 3.096MWh

System Configuration:12*258kWh ESS Cabinet Connected to 10/0.4kV-2500kVA Transformer

Benefits:

Est. Total Discharge: 998.998 MWh

System Efficiency: 88%


Post time: Jun-12-2025
Request Your Customized BESS Proposal
Share your project details and our engineering team will design the optimal energy storage solution tailored to your objectives.
Please enable JavaScript in your browser to complete this form.
contact

Leave Your Message

Please enable JavaScript in your browser to complete this form.